Hinton Park

Project description:

(Re-budgeted from FY08) This project includes design contract for all aspects of construction with park-planning design firm for design & construction documents for Phase I, to include eight (8) field complex, buildings & parking areas.   

2011
Phase I Construction includes initial park development to include site grading, drainage, Park Entrance Road, parking & landscaping features.
2012
Design Services for Phase II Development
2013
Phase II Development of park infrastructure, passive park amenities, and gathering locations.
2014
Design and construction of Phase III development to include multi-purpose inner trail system, outdoor educational features and interpretive signage.

Project summary:

Budgeted Amount:

  • Design - $325,000
  • Construction - $3,100,000
  • Total - $3,425,000

Status as of May 2009:

BMA approved the Hinton Park Conceptual Plan to include the overall concept of Hinton Park dividing the property into eight (8) distinct areas:  Hinton Arc, Hinton gateway, Hinton Sport, Hinton Play, Hinton Oaks, Hinton Fields, Hinton Meadows, and Hinton Crossings.  Components of each phase will be determined during the design development phase with recommendations by the Park Advisory board and Department Staff.